‘Big Odd’ inspects the progress of the construction of the new office building, the Football Association

‘Big Odd’ inspects the progress of the construction of the new office building, the Football Association

On January 18, Pol. Gen. Somyot Phumphanmuang President of the Football Association of Thailand Visit the area to check the progress of the construction of the FA Thailand Futsal and Match Operation Center within the area of ​​the Sports Authority of Thailand (SAT) Huamark, Gate 5

The latest construction project is in the process of piling 281 piles. At present, about 36 piles have been completed, accounting for 12% of the total. As planned, all piles will be driven on February 10. Approximately

Then proceed to the next step. is to dig the foundation soil, dig the soil, water tanks and underground septic tanks before entering the concrete foundation pouring form.

For the FA Thailand Futsal and Match Operation Center building project within the Sports Authority of Thailand (SAT) area, the construction period is 341 days, starting on January 4, 2022 and ending on December 15, 2022.