Check the non-flowing water point. Bangkok – Samut Prakan 29, 30 and 31 May ’23

next Tuesday, May 30, 2023 from 10:00 PM to 5:00 AM the next day. The 1,000 mm diameter main sluice needs to be closed to repair the leaking main sluice at Khlong Rang Kaew, Rama II Road, resulting in weak to non-flowing water supply. in the following areas

• Rama 2 Road, starting from Khlong Bang Khun Thian to Kanchanaphisek Road intersection (odd-numbered side from Soi 31 to Soi 71 and even-numbered side from Soi 20 to Soi 70)

• Sanam Ngam Charoen Road From Rama II Road intersection to Wat Tha Kham intersection (Odd numbered side from Soi 1 to Soi 19 and even numbered side from Soi 2 to Soi 16)

• Sakae Ngam Road, odd-numbered side from Soi 1 to Soi 13, and even-numbered side, from Soi 2 to Soi 14.

• Bang Khun Thian Road From the intersection of Rama 2 Road to the railway (Odd numbered side from Soi 9 to Soi 11 and even numbered side from Soi 12 to Soi 16)

• Bang Khun Thian-Chai Talay Road, even side, from Soi 2 to Soi 16/1

• Tha Kham Road