EEC closes job search for partners Go through the pile driving 4 mega projects

EEC announces closure of jobs for joint venture partners in 4 main infrastructures After signing with “GPC” as the last group, grabbed Laem Chabang Port 3, showing a total investment of more than 600 billion baht, moving forward to piling gradually open for service in 2025

Eastern Special Development Zone (EEC) Project It is an area development project from the development of the eastern seaboard area that has been known for more than 30 years, known as Eastern Seaboard The EEC project focuses on the development of 3 provinces in the eastern region, namely Rayong, Chonburi and Chachoengsao. goal to raise the country’s competitiveness

Kanit Sangsuphan, secretary-general of the Eastern Economic Corridor Policy Committee (OHEC) Revealed after the joint investment contract signing ceremony Laem Chabang Port Development Project Phase 3 in Port F Port on Nov 25, stating that today (25 Nov) is an announcement that the job is closed for private investment. Develop 4 main infrastructures in the EEC Because today it is considered that the goal of joint investment in infrastructure has been achieved. All 4 projects have private investment. and ready to start developing the project according to the plan

for 4 Core InfrastructureOccurring in the EEC consists of high-speed trains (high-speed trains) connecting three airports. U-Tapao Airport Project and Eastern Aviation City Map Ta Phut Port Project and Laem Chabang Port Project Phase 3 causingThe total investment amount is over 654,921 million baht. Divided into private investment of 416,080 million baht and joint venture capital of 238,841 million baht.

In which these projects, the private sector has offered a government return of 440,193 million baht and resulted inThe state has a net return. After deducting from the joint investment, it is worth 201,352 million baht. Therefore, it can be confirmed through the value of these investments that The EEC is not a project that uses government investment to develop during the time when the government has to manage the budget. But the EEC is a project that is a joint venture between the state and the private sector. It will also cause investor confidence. Increase investment value in the EEC area and the country as well

“4 Infrastructure The EEC has been continually signing cooperation since 2019 and is now in the process of preparing to start construction. For example, the current high-speed rail project EEC has already delivered 98% of the area between Suvarnabhumi – U-Tapao and the remaining 2% will be delivered in January, which the private sector has now entered the area. Cleared the work to prepare for construction.”

The timeline of the four main infrastructures in the EEC includes:

Map Ta Phut Port Project, Phase 3

  • Signed 1 Oct. 2019

delivery area Issue a letter of authorization to start construction (NTP) divided into

  • Phase 1 in 2021
  • Phase 2 in 2024
  • Scheduled to open in 2026

High-speed rail project connecting 3 airports (Don Mueang, Suvarnabhumi, U-Tapao)

  • Signed 24 Oct. 2019
  • delivery area Issue a permit to start construction (NTP) in 2022
  • Scheduled to open in 2026

U-Tapao Airport Project and Eastern Aviation City

  • Signed 19 June 2020
  • delivery area Issue a permit to start construction (NTP) in 2022
  • Scheduled to open in 2025

Laem Chabang Port Project Phase 3

  • Signed 25 Nov 2021

delivery area Issue a letter of authorization to start construction (NTP) divided into

  • Phase 1 in 2023
  • The second period in 2027

scheduled to open

  • Phase 1 in 2025
  • The second period in 2029

.