The Royal Thai Law enforcement has ordered the suspension of all Rama 2 jobs until August 14 – the h2o collapsed and the motor vehicle crashed.

The Highways Department has ordered the suspension of all Rama 2 tasks until August 14, after water was trapped in the canvas of the Rama 2 Tollway construction venture and leaked into the vehicle. To velocity up the hole in the water that is held out of the canvas at each and every pole. Install strengthened fall defense nets to be solid and protected.

In the circumstance of social media reporting information of flooding, a canvas from the Rama 2 Tollway building project fell into a motor vehicle on the expressway in the Samae Dam spot of ​​Bang Khun Thian District, Bangkok, resulting in the glass to shatter and the roof to collapse. The incident took place on the night time of 11 August.

Currently (12 August 2022), Mr. Saksiam Chidchob, the Minister of Transportation, that he has now purchased the Highways Department to Luang went to the place to examine and correct it quickly. This space is in the elevated highway building challenge on Highway No. 35, Thon Buri – Pak Tho Road (Rama 2), at the intersection of Bang Khun Thian – Ekachai.

Uncovered water trapped in the space of ​​the tarpaulin substance that experienced been dropped. for creating crossbars fell on the roof of the car thanks to ongoing significant rain But no a person was injured or killed. by taking away the weakened automobile from the scene

Mr Sak Siam mentioned that the officers of the Highways Division and contractors just after the accident Go satisfy the wounded human being at the Samae Dam space law enforcement station.To commence with, the contractor is prepared and ready to recover and compensate for all compensation from the event.

Study far more Order to stop the construction of Rama 2, starting up from 8-12 August Security scans.

Buy to cease development until August 14

to stop recurrence There are holes in the canvas to make it possible for drainage. And use a tighter rope to raise stability to reduce this from happening all over again. Prepared to inspect and make improvements to safety in the building region to be safer and extra safe.

In addition, the contractor has ordered to punish the supervisor. and stability officers to wait around for 3 times with no spend and has been summoned to alert in writing A further has requested all the development jobs. Verify the canvas made use of to deal with all setting up supplies. It is still in the rainy time.

Now in the interval of purchasing to end all development initiatives on Rama 2 Road among 8-12 August, the Director Standard of the Highways Office has requested to stop the building get the job done until finally August 14 to check functioning specifications.

Read related information.

Enjoyment! The drinking water in the canvas of the Rama 2 unexpected emergency development project fell into the car and damaged it.