ACV affirms doing the correct factor, not canceling the bidding outcomes of package deal 4.7 of Lengthy Thanh airport
Particularly, the consortium member, Hoang Lengthy Building Funding Company – JSC (nationwide bidding community quantity VN2800177056), has been suspended from the system from June 30, 2024 till the time of approval of the checklist of contractors assembly technical necessities.
The outcomes of the analysis of the above technical proposal paperwork adjust to the necessities of the bidding paperwork (BID) and the provisions of the regulation on bidding.
Disagreeing with ACV’s response, Deo Ca Group continued to ship a second petition requesting to cancel ACV’s bidding outcomes.
Within the doc dated August 21, 2024, ACV continued to affirm: The bidding paperwork for package deal 4.7 have been ready in keeping with type 03B (E-Building and set up bidding paperwork, one part, two envelopes) issued with Round No. 06/2024/TT-BKHĐT dated April 26, 2024 of the Ministry of Planning and Funding. The bidding paperwork have been authorized by the investor and posted on the nationwide bidding community to make sure publicity, transparency and equity in bidding.
“Through the time of making ready the bidding paperwork (BDS) for package deal 4.7 till the closing time of bidding, the inviting celebration has responded to all requests for clarification of the BDS from bidders and posted the clarification of the BDS on the bidding community in accordance with authorized laws,” ACV acknowledged.
Due to this fact, the truth that Deo Ca consortium, after ACV introduced the outcomes of the technical bid analysis, together with this error, and introduced the outcomes of the technical choice, had written feedback and extra info on the bidding community is totally inappropriate.
As well as, in keeping with ACV, the analysis of the technical proposal (TS) of the contractor was carried out by the inviting celebration in accordance with the provisions of regulation and the necessities of the Bidding Paperwork, particularly following the steps: Checking and evaluating the validity of the technical proposal; evaluating the capability and expertise; evaluating the technical proposal.
Solely contractors with legitimate bidding paperwork will probably be thought-about and evaluated for his or her capability and expertise; contractors with capability and expertise assembly the necessities will probably be thought-about and evaluated technically.
“Due to this fact, the three way partnership contractor’s self-assessment that its technical proposal meets technical necessities with out passing the validity evaluation step is baseless,” ACV affirmed.
Capability of the contractor consortium
In keeping with observers, the second consortium is thought to have loads of expertise in setting up runways and taxiways for plane aprons, having participated within the development of most main airports throughout the nation.
Taxiway apron class is taken into account a safety-related class in aviation and subsequently performs a number one position in any airport.
It’s recognized that beforehand, within the XL12 Mai Son – Nationwide Freeway 45 package deal of the North – South Expressway venture within the 2017-2020 interval, constructed by the consortium of Deo Ca Group Joint Inventory Firm – Hai Thach Building Funding Joint Inventory Firm – Hoang Lengthy Building Funding Company, contractor Hoang Lengthy was as soon as eradicated by the Minister of Transport Nguyen Van Thang due to gradual development.
In keeping with bidding specialists, The truth that Joint Enterprise 1 dedicated a violation is an plain or unforgivable mistake, irrespective of how small or massive.
If ACV accepts this, it can violate the bidding course of and severely violate the bidding regulation. At the moment, different contractors could have opinions and even sue this investor.