Home » News » Edwin Sodi: Corruption Scandal and Legal Battles

Edwin Sodi: Corruption Scandal and Legal Battles

Nearly three ​years after moving ⁤to ⁢blacklist controversial tenderpreneur Edwin Sodi, the City of Tshwane has failed to‍ even deliver the notice barring his company from‍ state work – citing the unusual excuse⁤ that it cannot find his address.Though, it took the ‌Sunday Times just one WhatsApp message⁤ to find Sodi, who said: “Write⁤ whatever you want to write.” ​

The leader of the DA opposition in tshwane, Cilliers Brink, accused members of‌ the metro⁤ management – ⁤run by a coalition that includes⁤ the ANC and ActionSA – of deliberately ⁣trying to sabotage the blacklisting of Sodi.

The self-declared ANC benefactor’s⁢ companies Blackhead Consulting and the G-5 Group ⁣(previously known as NJR Projects) have benefited⁤ from government contracts worth ​hundreds of millions of rand. Politicians⁣ with whom he has close ties⁢ include Deputy President Paul Mashatile.

In June ‌2023, the ⁢City of Tshwane announced that ⁣it had initiated a process to blacklist blackhead ⁢Consulting and NJR Projects after the entities, in a‌ joint ​venture with⁤ CMS‍ Water,‌ botched a‌ R291m project to refurbish the Rooiwal wastewater treatment plant ⁣ in⁤ Hammanskraal,north of Pretoria. The companies⁤ had failed ⁤to perform on the contract, which was awarded in 2019 and terminated by ⁢the council⁤ three years later.

The‌ failure to ⁣fix the wastewater plant⁣ led to a cholera outbreak in mid-2023 in which nearly 30⁣ people in the pretoria area died.

Multiple attempts were ​made ⁣on separate occasions to ⁢serve⁣ notice on ‌the affected companies and their directors through prescribed channels, including address confirmation via the central supplier database and ‍other lawful mechanisms. These efforts were ⁤complex by the entities being untraceable at‍ their​ registered⁤ locations

Sam Mgobozi, Tshwane mayor Nasiphi Moya’s spokesperson

The National ⁣Treasury’s procurement regulations allow ​government departments, state-owned entities and municipalities to blacklist companies and bar them from doing business with the state for up to ⁤10 years. Companies can be blacklisted for various forms of misconduct, including:

  • poor ‌performance;
  • bribery;
  • corruption;
  • bid-rigging;
  • fronting;
  • collusion;‌
  • lying about their broad-based‍ BEE status; and
  • presenting fraudulent tax clearance certificates.

The treasury ‍controls the blacklisting process​ and maintains a list ⁢of all those affected.

Though,​ almost three ⁤years after the ⁣Tshwane authorities pledged to⁢ blacklist ⁤Sodi and his ⁤partners, they have yet to⁢ do so, citing ⁤an inability to establish the companies’ addresses. Sodi is often seen in his ​nightclub, City of Tshwane and Stadium ​Projects

The City of Tshwane is overseeing both the Caledonian Stadium refurbishment and the Refilwe project. As ⁣of April 2021, the Refilwe project was ⁤reported ​to be ⁣95% complete, indicating substantial progress. However, the Caledonian ‍Stadium project has seen limited advancement.

According to a ​statement from ⁢Kamogelo Baloyi,the company’s general​ manager,the City of Tshwane ​had not yet decided whether to⁤ finalize any blacklisting procedures related to⁤ the contractor. Baloyi refuted claims of non-performance by Mologadi A Nape, attributing delays to ongoing contractual and legal disputes, including⁣ arbitration and ​enforcement proceedings.

Caledonian Stadium Refurbishment‌ Details

the Caledonian Stadium ⁢refurbishment was ‌budgeted at R120 million and‍ aimed to restore ⁣the historic ​stadium. The project’s purpose is to modernize the facility, possibly for sporting events and community use.

As of ⁣April 9, ‌2021, the ‌project was significantly behind schedule compared ⁣to the Refilwe project. The specific reasons for the delays beyond contractual disputes were ‌not detailed ‌in ‍the initial report.

example: The TimesLIVE report from April 2021 highlighted the disparity in​ progress between the two projects, ⁢noting the 95% completion of Refilwe versus the limited progress at Caledonian​ Stadium.

tshwane Sports Facilities and Mologadi A Nape

Mologadi A Nape was contracted by ⁢the City of Tshwane to undertake the⁤ Caledonian Stadium ⁣refurbishment.The company’s general manager,Kamogelo ​baloyi,stated that the project’s delays were linked to ongoing legal ‌and contractual disputes.

The City ‌of Tshwane ‌has not publicly released ‌detailed details regarding ​the‍ nature​ of these disputes or the status of the blacklisting consideration as‍ of January 25, 2026. A search of the City of Tshwane’s tenders and Contracts portal did not yield ⁣specific details on the Caledonian​ Stadium‍ contract or related legal proceedings as of this⁤ date.

evidence: Baloyi’s statement, as reported by TimesLIVE, directly⁤ attributes the delays to ongoing disputes,​ suggesting a complex legal situation surrounding the project.


You may also like

Leave a Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.