Lyon's New 5km Cycle Path: Next Steps - News Directory 3

Lyon’s New 5km Cycle Path: Next Steps

May 4, 2025 Catherine Williams News
News Context
At a glance
  • Lyon, France – The Metropolis of Lyon is expanding its network of cycle paths, known as the Lyonnais routes, with ⁤a new 5-kilometer section recently inaugurated in West...
  • A 5.2-kilometer segment ⁤connecting⁢ La Tour-de-Salvagny,⁤ Dardilly, and charbonnières-les-Bains is now open.
  • The development between La Tour-de-Salvagny and‍ Dardilly involved upgrading an existing ‍greenway, widening it to 3 meters at the stream crossing to improve safety.
Original source: actu.fr

Lyon Cycle Path Expansion Continues Amidst Mixed Reactions

Table of Contents

  • Lyon Cycle Path Expansion Continues Amidst Mixed Reactions
    • West Lyon Section Now Open
    • Future Development of Lyon Way 8
  • Lyon Cycle Path Expansion: Your Questions‍ Answered
    • What is the Lyon Cycle Path Expansion?
    • What’s New With the ⁤Expansion? What Sections Are Currently Open?
    • Has Construction of the West Lyon Section Been Fully Completed?
    • What is the Overall Goal of the Project?
    • When is the Entire ⁣Project Expected to Be Finished?
    • What Are‍ the Future Progress⁤ Plans?
    • What Are the Upcoming Construction Phases and Estimated Completion Dates?
    • Are There Any Delays Being Experienced?
    • What is the Status of the VL8 Route Overall?
    • Where Can I Find more information About the Project and Construction Delays?

Lyon, France – The Metropolis of Lyon is expanding its network of cycle paths, known as the Lyonnais routes, with ⁤a new 5-kilometer section recently inaugurated in West Lyon.‍ While the expansion is welcomed by cyclists, some residents, business owners, and drivers have expressed concerns. ⁣The project, slated for completion in 2026, aims ⁢to create a 27.3-kilometer path stretching from La-Tour-de-Salvagny in the west to Porte des Alpes in Saint-Priest in the east.

West Lyon Section Now Open

A 5.2-kilometer segment ⁤connecting⁢ La Tour-de-Salvagny,⁤ Dardilly, and charbonnières-les-Bains is now open. the VL 8 route utilizes Rue de Lyon in La-Tour-de-Salvagny,the old National Road 7 and the D307 in Dardilly,and the Paris route in Charbonnières-les-Bains. Construction on ⁢this section ‍began ‍in 2023.

The development between La Tour-de-Salvagny and‍ Dardilly involved upgrading an existing ‍greenway, widening it to 3 meters at the stream crossing to improve safety. Alternating traffic patterns were implemented to ‍reduce speeds ⁢entering La ⁢Tour-de-Salvagny.

On ⁤the‍ RD307 in Dardilly,‍ outside⁢ the main⁢ built-up area, the VL8 ⁣now features ⁢a mixed pedestrian and cyclist greenway, separated from the⁣ road by vegetation.

Future Development of Lyon Way 8

By 2030, the VL8 is projected to connect La⁢ Tour-de-Salvagny to ⁢Saint-Priest, traversing ⁢Tassin-la-Demi-Lune, Écully, Bron, and Lyon’s 5th, 2nd, 7th, and 8th arrondissements.

Upcoming construction phases include:

  • Route de Paris in Charbonnières: Work in⁢ progress, expected completion by ⁣mid-2026.
  • Tassin/Écully sector: Construction scheduled from May⁢ 2025 to March 2026.
  • Vincent Serre/Buyer sector: Work to begin in June 2025, concluding by year’s end.
  • University/Bloch sector: Ongoing⁣ work,with delivery anticipated in the first quarter of 2026.
  • Mermoz sector: Work underway until fall 2025.
  • Bron/St Priest/Campus de la Doua sector: Construction completed.

According to the “Ville à bicycle” association’s‍ Cyclopolis tool, some sections have faced delays, including ‍the University⁣ Bridge ‍development ⁤in the 7th arrondissement.Approximately 7.2 ‍kilometers of the project have been postponed, notably the Lyon peninsula crossing, Rue Marius Berliet, and the ZAC Bron-Parilly.

Lyon Cycle Path Expansion: Your Questions‍ Answered

This article provides a comprehensive overview of the ongoing cycle path expansion in Lyon, France. We’ll cover the latest developments, future plans, and potential delays, all in a helpful Q&A format.

What is the Lyon Cycle Path Expansion?

The Lyon cycle path expansion, also known as the ‍”Lyonnais ⁣routes,” is a large-scale project by the Metropolis of Lyon to extend its network of cycling infrastructure. The goal is to create a more extensive and⁢ accessible network for ‍cyclists throughout the city⁢ and surrounding areas.

What’s New With the ⁤Expansion? What Sections Are Currently Open?

A 5.2-kilometer segment has recently opened in West Lyon, connecting La Tour-de-Salvagny, ⁤Dardilly, and Charbonnières-les-Bains. This section, known as the‍ VL8 route, utilizes existing roadways and greenways.

Has Construction of the West Lyon Section Been Fully Completed?

Construction began in 2023. The section between La Tour-de-Salvagny and ‍dardilly involved upgrading an existing greenway. On the RD307 in Dardilly, a mixed pedestrian and cyclist greenway, separated from the road‍ by vegetation, is now open.

What is the Overall Goal of the Project?

The project aims to build a 27.3-kilometer cycle path. This continuous path‍ will stretch from La-Tour-de-Salvagny in the west to Porte des Alpes ‍in Saint-Priest in the east.

When is the Entire ⁣Project Expected to Be Finished?

The overarching project is ‍slated for completion in⁤ 2026.

What Are‍ the Future Progress⁤ Plans?

The VL8 route is projected to connect La Tour-de-Salvagny to Saint-Priest by 2030. This path will traverse Tassin-la-Demi-Lune, Écully, Bron, and several arrondissements within Lyon (5th, 2nd, 7th, and 8th).

What Are the Upcoming Construction Phases and Estimated Completion Dates?

Here’s a summary ⁢of the upcoming construction phases from the source material:

⁣ Route de ‍Paris in Charbonnières: Expected completion by ⁣mid-2026.

Tassin/Écully sector: Construction scheduled from ⁢May 2025 to March 2026.

Vincent Serre/Buyer sector: Work ⁤to begin in June 2025, concluding by the end of 2025.

University/Bloch sector: Ongoing work, with delivery anticipated⁢ in the first quarter of 2026.

mermoz sector: Work underway until fall 2025.

⁣ Bron/St Priest/Campus de la Doua sector: Construction completed.

Are There Any Delays Being Experienced?

Yes.Several sections have faced delays,‍ including the University Bridge⁣ development in the 7th arrondissement. Approximately 7.2 kilometers of the project⁤ have been postponed, specifically, the lyon peninsula⁢ crossing, Rue Marius‍ Berliet, and the ZAC Bron-Parilly.

What is the Status of the VL8 Route Overall?

The VL8 route, when fully realized, ⁣will connect La⁣ tour-de-Salvagny to saint-priest. It will pass through Dardilly, Bron, and other surrounding areas.

Where Can I Find more information About the Project and Construction Delays?

The “Ville à bicycle” association’s Cyclopolis tool often provides updated information.

Share this:

  • Share on Facebook (Opens in new window) Facebook
  • Share on X (Opens in new window) X

Worth a look

  • Bangladeshi Travel Vlogger Salahuddin Sumon Promotes Storytelling and Responsible Tourism
  • Sheinbaum Offers Rosario Castellanos University to Students Rejected by UNAM

Related

company, Cycle paths, Lyonnais tracks

Search:

News Directory 3

News Directory 3 catalogs US newspapers, news services, newsstands and digital news outlets across all 50 states. Browse local publishers by city, state, or topic, and follow current headlines linked back to their original sources.

Quick Links

  • Disclaimer
  • Terms and Conditions
  • About Us
  • Advertising Policy
  • Contact Us
  • Cookie Policy
  • Editorial Guidelines
  • Privacy Policy

Browse by State

  • Alabama
  • Alaska
  • Arizona
  • Arkansas
  • California
  • Colorado

© 2026 News Directory 3. All rights reserved.
For contact, advertising, copyright, issues email: office@newsdirectory3.com