Minister Ivanov: Botevgrad-Mezdra Traffic Launch End June

April 9, 2025 Catherine Williams News
News Context
At a glance
  • ‍ Delays in the repair⁢ of the telish-Radomantsi section of the Lukovit-Pleven road have drawn criticism, according to Minister of regional Development and Public Works⁤ Ivan Ivanov.The minister...
  • ‍ Ivanov stated‍ the critical question is why the necesary repairs have not yet been completed.
  • Ivanov asserted his readiness to commence the major repair‍ of the Telish-Radomantsi section as soon as ongoing investigative actions conclude and the prosecutorS office grants permission to proceed.
Original source: fakti.bg

Road Repair Delays⁢ Spark Controversy in Lukovit-Pleven Project

Table of Contents

  • Road Repair Delays⁢ Spark Controversy in Lukovit-Pleven Project
    • Minister blames Previous Management for Inaction
    • Repair Work Contingent on Investigations
    • Traffic Rerouting Expected by Summer
    • Botevgrad-Vidin Route Completion Projected for‍ 2029
    • Accountability Demanded from RIA Leadership

‍ Delays in the repair⁢ of the telish-Radomantsi section of the Lukovit-Pleven road have drawn criticism, according to Minister of regional Development and Public Works⁤ Ivan Ivanov.The minister addressed the issue in an interview.

Minister blames Previous Management for Inaction

‍ Ivanov stated‍ the critical question is why the necesary repairs have not yet been completed. He suggested the question should be ⁢directed to the previous minister, Ivan Shishkov. “The repair should ⁤have been done a long time ago,” Ivanov said, “but a contractor has not been selected. But this is not a reason to justify.”
⁤

Repair Work Contingent on Investigations

Ivanov asserted his readiness to commence the major repair‍ of the Telish-Radomantsi section as soon as ongoing investigative actions conclude and the prosecutorS office grants permission to proceed. He added that the primary ‍repair of⁢ the Lukovit-Pleven road hinges on the completion of the Botevgrad-Mezdra section and the release of Lot 1 at Hemus Motorway.

Traffic Rerouting Expected by Summer

⁤ ⁢ The regional minister anticipates that traffic currently diverted past Telish will revert to its original route once the Botevgrad-Mezdra section is operational. “This section should be launched ⁢at the end of June,” Ivanov said.
‍ ‍

Botevgrad-Vidin Route Completion Projected for‍ 2029

⁤ The Road infrastructure ⁣Agency (RIA) projects the entire Botevgrad-Vidin route will be‍ completed by ‍2029.
⁣

Accountability Demanded from RIA Leadership

When questioned about potentially ⁣requesting⁢ the resignation of the RIA head, Ivanov emphasized the importance of accountability. “I will want accountability regarding all the signals that enter⁢ the RIA,” he stated.⁢ “They have been reporting them from the two months⁤ in which I am there – I ‍see that they are doing their job.”

⁢ Ivanov added, “The work of the RIA leadership is to follow this political will and this rhythm that I have set. And they are following it right now. The moment they break this rhythm, the moment ‍they do not do their job – ⁤everyone will be released. I guarantee it. On⁤ the check I have assigned if it shows even the slightest hint ⁣of any pass ‍- this⁣ employee will be removed, no matter what ⁤level it will be.”
⁢ ⁣

# Road repair Delays: Your Questions Answered

Are you following the news about road repairs in Bulgaria? Specifically,the delays in the Lukovit-Pleven road project have become ⁤a source of‍ controversy.Let’s dive into the⁣ specifics,⁢ covering the delays,‍ the reasons behind them, and what the future holds.

## What’s the Controversy Surrounding the Lukovit-Pleven Road Project?

the primary issue revolves around delays in the repair of the Telish-Radomantsi section of the⁤ Lukovit-Pleven road. These delays have stirred criticism, prompting statements from Minister of Regional Development and Public Works, Ivan Ivanov.

##⁣ Who’s Being ⁤Blamed for These Road Repair Delays?

Minister Ivanov has pointed the finger at the previous management for ⁤the inaction. he highlighted that the necesary repairs should⁢ have been completed much earlier. He stated that this is not a justified reason⁣ for the ⁢delays.

## Why Haven’t the Repairs on the Telish-Radomantsi section Been Completed?

The primary reason, according to Minister Ivanov, is the failure to select ⁤a contractor for the repair work.

## What’s Preventing the ‍Commencement of⁢ Repairs on the ⁣Telish-Radomantsi Section?

The major repairs on the Telish-Radomantsi ⁣section are contingent on the⁤ conclusion⁤ of ongoing investigative actions. Specifically, the Ministry is awaiting permission from the prosecutor’s ⁤office to proceed. additionally, the⁣ minister added ⁤that ⁣the Lukovit-Pleven‍ road’s repair relies on the completion of the Botevgrad-mezdra⁤ section and the release of Lot 1⁤ at Hemus Motorway.

## When ⁤Can We Expect Traffic to Revert ⁤to the Original Route?

The regional minister anticipates that traffic diverted away from Telish will be able to return to its original route once the Botevgrad-Mezdra section becomes operational. This section ⁢is targeted to be⁣ launched⁣ by the end‍ of June.

## When is the ‍Full Botevgrad-Vidin Route Expected ⁤to be Completed?

the⁣ Road Infrastructure ⁢Agency (RIA) projects‍ that the entire Botevgrad-Vidin route will be‍ completed by ‍2029.

## What dose the Minister Say ⁤About Accountability Within the RIA?

Minister Ivanov has emphasized the importance of accountability within the⁢ Road Infrastructure Agency (RIA).

## Could the Head⁣ of the RIA Face Resignation?

When questioned about the potential⁤ for requesting the RIA head’s resignation, Minister Ivanov emphasized that he will demand accountability regarding all the signals entering⁣ the RIA. He has stated he‍ is monitoring their work.If thay fail, ⁢action will be taken.

## Summary of Key⁣ Project Timeline

Here’s a summary of the key timelines mentioned in ⁣the article:

Project Section Expected Timeline
Botevgrad-Mezdra Section Launch End of June (estimated)
Full Botevgrad-Vidin Route completion 2029 (projected)

Share this:

  • Share on Facebook (Opens in new window) Facebook
  • Share on X (Opens in new window) X

More on this

  • Wordle Answer for October 4: Hints and Solution for Today’s Puzzle
  • Trump Leaks Senator Cotton’s Phone Number Over Sunshine Protection Act

Related

Search:

News Directory 3

News Directory 3 catalogs US newspapers, news services, newsstands and digital news outlets across all 50 states. Browse local publishers by city, state, or topic, and follow current headlines linked back to their original sources.

Quick Links

  • Disclaimer
  • Terms and Conditions
  • About Us
  • Advertising Policy
  • Contact Us
  • Cookie Policy
  • Editorial Guidelines
  • Privacy Policy

Browse by State

  • Alabama
  • Alaska
  • Arizona
  • Arkansas
  • California
  • Colorado

© 2026 News Directory 3. All rights reserved.
For contact, advertising, copyright, issues email: office@newsdirectory3.com