Thieracher School Planning Rejected
- The loan failed with 495 no votes, leaving the school children in temporary containers.
- “I am very disappointed for the village,” said the local council president of Thierachern, commenting on the outcome of Sunday’s vote in the community located west of Thun.
- Of the 1,930 eligible voters,45.8% participated in the vote on the CHF 785,000 planning loan, with 385 voting yes and 495 voting no.
Thierachern Rejects School Planning: Refurbishment Project Fails
Table of Contents
- Thierachern Rejects School Planning: Refurbishment Project Fails
- Thierachern School Project: Frequently Asked Questions
- What happened to teh Kandermatt school project in Thierachern?
- why was the school project rejected?
- What are the key points of the Thierachern school project rejection?
- What are the planned next steps for the school?
- When did the project begin,and what has already been spent?
- Where will the students be taught simultaneously occurring?
- What were the initial and revised cost estimates for the construction project?
- What dose the rejection of the loan entail?
- Q&A Summary
The loan failed with 495 no votes, leaving the school children in temporary containers. Concerns over costs may have swayed the vote.

Key Points:
- A planning loan for the kandermatt school system was rejected with 495 no votes.
- Opponents raised concerns about the planned construction costs of 15 million francs.
- Planning costs already allocated will now be written off.
- Students will remain in temporary container classrooms next to the existing 50-year-old school building.
“I am very disappointed for the village,” said the local council president of Thierachern, commenting on the outcome of Sunday’s vote in the community located west of Thun.
Of the 1,930 eligible voters,45.8% participated in the vote on the CHF 785,000 planning loan, with 385 voting yes and 495 voting no.
“The verdict is clear and means that we have to go back to square one with the Kandermatt school system,” the council president stated, acknowledging the project’s long and troubled planning history.
Project Timeline
The project began in June 2022 with the approval of CHF 270,000 for a project competition at the municipal assembly.Two years later, an additional CHF 175,000 was allocated for further planning and a preliminary project.
The recent vote was to secure an additional CHF 785,000 for the advancement of the construction project. Because the total commitment exceeded CHF 1 million, the loan required a public vote.
Opposition Concerns
Prior to the vote, an anonymous leaflet circulated in Thierachern, advocating against the schoolhouse loan. The “bourgeois committee for a reasonable expenditure policy,” as the leaflet identified the group, targeted the total estimated costs for the school expansion.
While initial estimates exceeded CHF 19 million, the municipal council reduced the limit to CHF 15 million following public concerns.
The opposition claimed the new school should only cost CHF 7 million. The municipal council countered, emphasizing that the project included both an expansion and a renovation of the existing building. The council president stated, “we don’t plan a Rolls-Royce,” but the message did not resonate with voters.
Planning Costs “Lost”
Consequently of the loan’s rejection, the municipal council stated that the school project cannot proceed as planned. The previous planning costs will now be written off.
“Further delays can be expected,” the local council stated, adding that they will discuss the next steps and “inform the population in due course.” In the meantime, primary students will continue to be taught in containers and in the existing school building, which is over 50 years old.
The council president noted that the authors of the leaflet remain anonymous.
Thierachern School Project: Frequently Asked Questions
What happened to teh Kandermatt school project in Thierachern?
The Kandermatt school project, which aimed to renovate and expand the existing school, was rejected by voters in Thierachern. A planning loan of CHF 785,000 was voted down,with 495 votes against and 385 in favor.
why was the school project rejected?
The primary reason for the rejection appears to be concerns over the projectS cost. The planned construction costs were estimated at CHF 15 million.An opposing group, identified in an anonymous leaflet as the “bourgeois committee for a reasonable expenditure policy,” advocated against the loan, citing the high costs.
What are the key points of the Thierachern school project rejection?
A planning loan was rejected by voters.
Opponents raised concerns about the construction costs.
Previous planning costs will now be written off.
Students will remain in temporary classrooms.
What are the planned next steps for the school?
The municipal council has stated that the school project cannot proceed as initially planned. They will discuss the next steps and “inform the population in due course.” Further delays are expected.
When did the project begin,and what has already been spent?
The project began in June 2022 with the approval of CHF 270,000 for a project competition. an additional CHF 175,000 was later allocated for further planning and a preliminary project.
Where will the students be taught simultaneously occurring?
Until a new plan is in place,primary students will continue to be taught in temporary container classrooms and the existing school building,which is over 50 years old.
What were the initial and revised cost estimates for the construction project?
Initial estimates for the project exceeded CHF 19 million. The municipal council reduced this to CHF 15 million in response to public concerns.
What dose the rejection of the loan entail?
The rejection of the loan means the project is effectively back to square one.The CHF 785,000 planning loan was intended to advance the construction project which required a public vote because the total commitment exceeded CHF 1 million.
Q&A Summary
| Question | Answer |
|—————————————————————|—————————————————————————————————————————————————————————————–|
| What happened to the school project? | The project was rejected by voters. |
| Why was it rejected? | Concerns over the CHF 15 million costs |
| What happens next? | The council will discuss the next steps and inform the public. Primary students remain in container classrooms and the existing school buuilding. |
| When did the project start? | June 2022 |
| How much has already been spent? | CHF 445’000 (CHF 270,000 + CHF 175,000) |
| Where do students attend classes now? | Container classrooms and the 50-year-old school |