AS Roma Pietralata stadium project authorized for construction
- The administrative process for AS Roma’s new stadium in the Pietralata district has reached a definitive milestone.
- The authorization was formalized by government commissioner Massimo Sessa, who signed the measure following the final meeting held at the Ministry of Infrastructure and Transport.
- Minister for Sport and Youth Andrea Abodi praised the accelerated timeline on social media platform X.
The administrative process for AS Roma’s new stadium in the Pietralata district has reached a definitive milestone. The decisional services conference (Conferenza dei Servizi decisoria) issued a positive opinion on the technical and economic feasibility project, authorizing the construction of the facility. The approval, finalized in 90 days rather than the standard 270, allows the club to proceed toward the execution phase, with project completion targeted for 2031.
Official Authorization and Administrative Timeline
The authorization was formalized by government commissioner Massimo Sessa, who signed the measure following the final meeting held at the Ministry of Infrastructure and Transport. Rome Mayor Roberto Gualtieri, acting as sub-commissioner, co-signed the unique authorization, which is now immediately effective. This development concludes four years of administrative planning and provides the necessary legal framework for the club to begin drafting the final executive project.
https://x.com/andreaabodi/status/2104551874216984689
Minister for Sport and Youth Andrea Abodi praised the accelerated timeline on social media platform X. He stated:
“It is a strong, clear, and unequivocal signal of what we are capable of doing when the tools are configured and made available to qualified people.” — Andrea Abodi, Minister for Sport and Youth
Construction Schedule and UEFA Euro 2032 Stakes
The project’s timeline is closely linked to Italy’s preparations for UEFA Euro 2032. While the stadium is expected to be completed by 2031, Mayor Gualtieri indicated that the city aims to break ground in March 2027, coinciding with the club’s centennial celebrations. Gualtieri suggested that if the construction proceeds according to the two-and-a-half-year estimate, the facility could be ready for use by late 2029.
Commissioner Sessa has tasked the municipal government with ensuring the project remains on track for the tournament, though he clarified that the construction deadline remains valid regardless of whether the Pietralata site is ultimately selected by UEFA as a host venue. Minister Abodi confirmed that the official list of candidate stadiums for Euro 2032 will be submitted to UEFA within three days of the conference’s conclusion.
Local Development and Future Public Impact
Municipal officials view the stadium as a catalyst for urban regeneration in the Pietralata area. Massimiliano Umberti, president of Rome’s Fourth Municipality, described the project as an opportunity to integrate sports facilities with improved public infrastructure, mobility, and community services. Umberti emphasized that the municipality intends to prioritize public interest and territorial enhancement throughout the subsequent phases of development.
The next steps involve the City of Rome launching a call for interest regarding the concession of the area. While the tender is open to third-party entities, AS Roma retains the right to match any competing offers as the original project proponent.

Broader City Infrastructure Goals
Beyond the Pietralata project, the government is focusing on the revitalization of the Stadio Flaminio. Minister Abodi noted that the progress made on the Roma stadium should serve as a model for the Flaminio project, which he described as a significant cultural and social undertaking for the city. He expressed hope that the efficiency demonstrated by the current administrative procedure would provide a stimulus for the ongoing efforts to restore the historic stadium to active use.