Will the Dunchon Jugong situation be resolved after 40 days of construction suspension? Seoul city proposes arbitration plan

City recommends “accepting each other’s demands and the union delegates full power to SH LH”

A view of the Dunchon Jugong reconstruction project, where construction was halted due to a conflict between the union and the construction project team.

[연합뉴스 자료사진]

(Seoul = Yonhap News) Reporter Yoon Bo-ram = The Seoul Metropolitan Government prepared an arbitration plan and presented it to both sides in relation to the reconstruction project of Dunchon Jugong Apartment in Gangdong-gu, Seoul, which had been suspended for 40 days due to a conflict between the union and the construction team.

According to the Seoul Metropolitan Government on the 1st, the city prepared an arbitration plan reflecting the opinions of the union and the construction project team regarding this situation and delivered it to both sides on the 30th of last month.

It is reported that the union and the construction project team sat down at the negotiating table on the 27th of last month through mediation of the city of Seoul.

This is the first time that the city has directly proposed an arbitration plan. The arbitration proposal, which had been previously discussed and rejected by both sides, came out through the coordinator’s activity report.

The city no longer discusses the validity or invalidity of the ‘June 25, 2020 Modified Contract’, which is the core of the conflict in the arbitration plan. After applying for re-verification with ONE, it was suggested that the contract be changed to reflect the results.

In addition, it was recommended to the construction project group to accept the union’s request to upgrade the finishing materials and change the contract system and resume construction within 30 days.

In addition, the City shall accept the changes in response to the request of the construction project team for financial cost loss due to delay in pre-sale, extension of the appropriate construction period to ensure quality, suspension or resumption of construction, etc. For this purpose, matters to be delegated to the Land and Housing Corporation (SH·LH, project agent) are decided through a resolution of the general meeting, and the union and construction project group do not raise any objection to the project agent’s judgment.

This means that in the process of resolving disputes between the two sides, the decision of the city must be followed only to a certain extent, and it is based on Article 28 (1) of the Urban and Residential Environment Improvement Act.

According to the provisions, if the maintenance project is delayed for a long period of time or if it is recognized that it is difficult to continue the maintenance project implemented by the association or the owner of land, etc. due to a dispute over rights, etc. or have the Land and Housing Corporation implement a maintenance project instead.

A city official said, “We have been making efforts to mediate the conflict between the union and the construction project team for fear of harm to the good members, and this arbitration plan is to open the door to a resolution of the situation in order to resume construction quickly,” said a city official. A final decision will be made on whether to accept the arbitration proposal after a general meeting,” he said.

“The joint inspection of the union will be carried out fairly and strictly in accordance with laws and regulations, independent of arbitration efforts,” he said. From the 23rd of last month to the 3rd of this month, the city is jointly inspecting the overall operation of the Dunchon Jugong Reconstruction Association with the Ministry of Land, Infrastructure and Transport and Gangdong-gu Office.